In April 2016 Manchester eScholar was replaced by the University of Manchester’s new Research Information Management System, Pure. In the autumn the University’s research outputs will be available to search and browse via a new Research Portal. Until then the University’s full publication record can be accessed via a temporary portal and the old eScholar content is available to search and browse via this archive.

OPTIMISING NET PRESENT VALUE USING PRIORITY RULE-BASED SCHEDULING

Tantisuvanichkul, Vacharee

[Thesis]. Manchester, UK: The University of Manchester; 2014.

Access to files

Abstract

This research is focused on project scheduling with the aim to capture the monetary objectives of the project in the form of the maximisation of Net Present Value (NPV). In addition, this research is also highlighted key project management practices and scheduling methods. Project scheduling is very attractive for researchers and it has recently been drawn considerable attention because of the high cost of capital and the significant effect of the time value of money. This is the principal motivating factor behind this study.Project-scheduling problem is solved by priority rule-based heuristic methods in this study. The idea behind heuristic algorithms is to rank the activities by some rules. This research proposes a new rule called m-CCF with improved performance from the existing one. The m-CCF is also embedded in serial and parallel schedule generation schemes and is extended by implementing in a forward and backward strategy. The experiments are conducted to evaluate the performance of the proposed technique measuring the NPV generated for a particular project. This research also presents a framework summarising the previous research on project scheduling techniques. It is found that the m-CCF results in higher NPVs than any other heuristics. A series of different projects are examined to validate the potential of the m-CCF technique. The main findings of the research discover that the m-CCF is worthwhile to be employed in priority rule-based scheduling technique. Furthermore, the main findings suggest that it is beneficial to utilise forward-backward solution for scheduling improvement and selecting the schedule with the largest NPV among those available.In conclusion, this research contributes to existing knowledge by developing the combination of m-CCF priority rule methods and backward–forward scheduling. This can be considered as a good direction to develop further heuristics that can be exploited as a powerful tool in project planning and control systems.

Keyword(s)

Project scheduling

Bibliographic metadata

Type of resource:
Content type:
Form of thesis:
Type of submission:
Degree type:
Doctor of Philosophy
Degree programme:
PhD Management of Projects
Publication date:
Location:
Manchester, UK
Total pages:
241
Abstract:
This research is focused on project scheduling with the aim to capture the monetary objectives of the project in the form of the maximisation of Net Present Value (NPV). In addition, this research is also highlighted key project management practices and scheduling methods. Project scheduling is very attractive for researchers and it has recently been drawn considerable attention because of the high cost of capital and the significant effect of the time value of money. This is the principal motivating factor behind this study.Project-scheduling problem is solved by priority rule-based heuristic methods in this study. The idea behind heuristic algorithms is to rank the activities by some rules. This research proposes a new rule called m-CCF with improved performance from the existing one. The m-CCF is also embedded in serial and parallel schedule generation schemes and is extended by implementing in a forward and backward strategy. The experiments are conducted to evaluate the performance of the proposed technique measuring the NPV generated for a particular project. This research also presents a framework summarising the previous research on project scheduling techniques. It is found that the m-CCF results in higher NPVs than any other heuristics. A series of different projects are examined to validate the potential of the m-CCF technique. The main findings of the research discover that the m-CCF is worthwhile to be employed in priority rule-based scheduling technique. Furthermore, the main findings suggest that it is beneficial to utilise forward-backward solution for scheduling improvement and selecting the schedule with the largest NPV among those available.In conclusion, this research contributes to existing knowledge by developing the combination of m-CCF priority rule methods and backward–forward scheduling. This can be considered as a good direction to develop further heuristics that can be exploited as a powerful tool in project planning and control systems.
Keyword(s):
Thesis advisor(s):
Language:
en

Record metadata

Manchester eScholar ID:
uk-ac-man-scw:230961
Created by:
Tantisuvanichkul, Vacharee
Created:
11th August, 2014, 16:38:52
Last modified by:
Tantisuvanichkul, Vacharee
Last modified:
20th October, 2014, 13:02:22

Can we help?

The library chat service will be available from 11am-3pm Monday to Friday (excluding Bank Holidays). You can also email your enquiry to us.